The fitting up

In adjustable base plate, you fit up different heights vertical (2m wall side and 3m space side) in order to use the longest vertical as a guard rail.

<––

In accordance with the site,
every others solutions are possible.

––>

SCAFFOLDINGS
Presentation
Multilevel, multidirectional scaffolding
The tubular structure
Principal components
Advantages
The fitting up
Shemas
Maximum working load
Platform’s distribution
Reference
Realisation sample

Anchorage

– One anchor pieces every 24 m2 for uncovered scaffolding.
– One anchor pieces every 12 m2 for covered scaffolding

Fitting up with standard vertical and 0.50 m starting system (0.50m starting vertical + integral adjustable base plate)

<––

Linear protection with debris shield and stability frame.

––>

Stability

A scaffolding must be longitudinally blocked by diagonal face braces or stability frames